Ethiopia reaffirms GERD 2nd filling in coming rainy season - Welcome

Nested Portlets

Asset Publisher

ለታላቁ ህዳሴ ግድብ ግንባታ ባለፉት 11 ወራት ከ984 ሚሊዮን ብር በላይ ተሰበሰበ Fri, 17 Jun 2022

ለታላቁ የኢትዮጵያ ህዳሴ ግድብ ግንባታ የ2 ነጥብ 4 ሚሊዮን ብር ድጋፍ ተደረገ Wed, 15 Jun 2022

ታንዛኒያ ሕዳሴ ግድቡ ሁሉንም የተፋሰሱ ሀገራት ተጠቃሚ እንደሚያደርግ ገለጸች Wed, 8 Jun 2022

በምስራቅ ሀረርጌ ዞን ለኅዳሴ ግድብ 42 ሚሊየን ብር ተሰበሰበ Wed, 8 Jun 2022

Facts about the Dam

× LOCATIONBenishangul-Gumuz region, Ethiopia.
× CONSTRUCTION STARTED:2011 G.C.
×Area: 1,874 sq KM
× RESERVOIR CAPACITY: 74 billion cubic metres

About GERD

Asset Publisher

Asset Publisher

Ethiopia reaffirms GERD 2nd filling in coming rainy season

Ethiopia reaffirms GERD 2nd filling in coming rainy season

According to the news source of ENA , The Ministry of Water, Irrigation and Energy and executive council member the public participation to the dam has reaffirmed second round filling of Grand Ethiopian Renaissance Dam (GERD) in the coming rainy season and refuted the unfair claim of monopoly over the Nile waters.
Water, Irrigation and Energy Minister, Engineer Sileshi Bekele (Ph.D) said that Ethiopia is negotiating for equitable and reasonable water utilization without causing significant harm to the downstream countries as unfair claim of the entire Nile waters and protecting the status quo would cause significant harm on its effort for development.
Sileshi further noted that the repeated narrative of Egypt and Sudan claiming that Ethiopia unilaterally filled the dam in the rainy season of 2020 is superficial. He added that the three countries have agreed as the stage-based construction of the dam is inseparable from the stage-based filling of the dam.
The second round filling of the dam retaining 13.5 billion meter cube will proceed in the coming Ethiopian rainy season. The dam fulfills all safety standards and is appreciated by experts of the downstream countries, he noted.
Ethiopia is committed to conclude the trilateral negotiation under the auspices of the African Union. The project has significant economic value for the East Africa by resolving the shortage of power supply and generating notable income.
GERD facilitates regional economic integration in power pool and build trust among the riparian countries.
GERD Manager Engineer Kifle Horo on his part indicated that 78.8 percent of the project has been completed. The second round filling and energy generating trial are next milestones of the project.

Asset Publisher

— 5 Items per Page
Showing 1 - 5 of 9 results.

About Us

Benefits of the Grand Renaissance Project

At the completion of the project, the average generation of 15,759 Giga watt hours per year will have a significant contribution to the national electricity system. The contribution of this project will be higher to reach the targets set by the rural electrification villages and to increase the supply from 44% to 90%.

The major components of the project

The Grand Ethiopian Renaissances Dam is being constructed for the purpose of generating electricity with total installed capacity of average annual energy production of about 15,759 GWh/yr.

Discharge rate about 1,547 m3/s.

The reservoir area will cover 1,874 square kilometers at full supply level of 640 meters above sea level maximum amd 590 metres minimum.

It has a 1.8 km length and 145 m height Roller Compacted Concrete dam.

Saddle Dam embankment of length 5.2 km and height 50 m.

The total storage volume is 74 billion cubic meters